Road Development Work in Downtown Area

Project Timeline:

Start Date: May 28, 2024
End Date: May 30, 2024 (weather permitting)

Work Details:

Southbound Side (3rd St to Alabama St):

  • Tx Dot will begin mill/inlay work on the southbound side.
  • Expect lane closures during this period.
  • Due to the one-way street configuration, parking spots along this route will be unavailable.

Northbound Side (2nd St to 4th St):

  • The following day, the focus shifts to the northbound side.
  • Residents and commuters should anticipate lane closures in this area as well.

Completion Date:

The northbound side work is scheduled to conclude on Thursday, May 30, 2024.

Parking Restrictions:

On Thursday, May 30th, the inside lane on the northbound side will be blocked. Please plan accordingly and find alternative parking arrangements during this time.

Work Hours:

Construction hours are from 7:00 AM to 5:30 PM. There will be no overnight closures.